位于Car-Parc Diem(原26号停车场)旁边的新热冷电联产厂(CHCP)正在建设中。

沿大学长廊的管道安装工程已接近完成,管道已安装于主路,回填工程正在进行中。 下周行人交通模式不会改变。

Significant phases in the construction that are upcoming are as follows:

  • Asphalt paving is scheduled for University Promenade on Saturday, September 29. It will begin at the north end of Calcia Hall and extend to the South end of Sprague Library. The west door of Dickson Hall will remain open via a temporary walk on the east side of University Promenade. The paving will be finished in one day, weather permitting.
  • On Monday, October 1, the University Promenade will reopen from University Hall to College Hall
  • The permanent rerouting of the Sprague Library potable water line has begun inside the existing fence line. The rear door of the library is currently closed and to be used as emergency egress only.
  • Piping installation has begun on the western edge of the campus behind Stone Hall and will continue south. Construction in this area has no direct impact on pedestrian or vehicular traffic, however everyone is reminded to be observant of construction vehicles moving in and out of the area.
  • Campus Shuttle service will remain available at the north end of University Hall via the new bus loop and bus stop.
  • The attached construction map shows the vehicular and pedestrian traffic patterns around campus.

All roadways and pedestrian routes will be clearly marked so the campus community can navigate construction areas easily. All buildings will remain open and accessible.

We will continue to issue regular updates on the progress of the construction by email and on our website.

Thank you for your continued cooperation and support with our effort to improve the University infrastructure.