October 5, 2012
Construction Update for Week of October 8
Posted in: CHCP Updates

位于CarParc Diem(原26号停车场)附近的新热冷电联产(CHCP)工厂正在建设中。
- 十月五日,由大学礼堂至书院礼堂的大学长廊将重新开放。
- 通往斯普拉格图书馆的管道部分仍在继续。
- The installation of the piping behind Stone Hall, and the future CELS building is continuing. On October 10 the contractor will be begin to extend the excavation between the new CELS building and Speech Hall toward Schmitt Hall.
- On October 8 a new electrical cable will be installed between Partridge and Calcia Halls. A power outage will be scheduled later in the month to make the final tie-in of the new line. Information regarding that tie-in will be disseminated as it becomes available.
- This construction map shows the vehicular and pedestrian traffic around campus.
All roadways and pedestrian routes will be clearly marked so the campus community can navigate around the construction areas easily. All buildings will remain open and accessible.
We will continue to issue regular updates on construction progress.
Thank you for your continued cooperation and support with our effort to improve the University infrastructure.