Construction Update for Week of January 28
Posted in: CHCP Updates, Construction News

欢迎所有的学生、教师和工作人员回来。
新的热冷电联产(CHCP)电厂正在建设中。 所有主要设备都已收到并已到位。 机械和电气系统的安装工作仍在继续,工厂将于2013年4月启动。
The recently installed mechanical gates have been placed in service. Only Montclair State vehicles and approved construction vehicles are permitted past the gates to the interior of the campus.
The underground piping distribution system installation is also progressing on schedule and the following should be noted:
- Construction continues in the Alumni Green and the rear exit of College Hall and the College Hall Bridge remain closed. A passage has been opened through the Alumni Green to access the Sprague Library and Morehead Hall from the University Promenade.
- The sidewalk on the east side of College Hall will be closed to pedestrian through traffic. To access Morehead Hall, you should travel through the Alumni Green from the lower Promenade.
- Lot-17 has been restored to use with the exception of the area around the new manhole.
- The entire roadway in front of Webster Hall is closed while the piping is being installed. The construction will continue and connect to the installed piping north of Stone Hall.
- Final tie-in work is being completed in the manhole on the University Promenade In front of University Hall.
- Final connection work is underway in Calcia Hall, Dickson Hall, Partridge Hall, Life Hall, University Hall and the Student Center.
All roadways and pedestrian routes will be clearly marked so the campus community can navigate construction areas easily. All buildings will remain open and accessible. Please see the campus construction map for details of areas under construction.
We will continue to issue regular updates on construction progress.
Thank you for your continued cooperation and support with our effort to improve the University infrastructure.